66-1243.Same; interconnection facilities; grant or lease, when. Any entity which, on or after January 1, 2004, constructs in this state new or expanded electric generation facilities having a capacity of at least 100 kilowatts may either grant or lease interconnection facilities to transmission operators, upon agreement between the entity and operator and approval by the commission.

History: L. 2004, ch. 120, § 4; July 1.